Online Course Support

Figure 3: Tornado Chart for Project X According to the Tornado Chart above, which task has the potential to cause the GREATEST IMPACT on the project’s OVERALL DURATION?

Question 6
Figure 3: Tornado Chart for Project X

According to the Tornado Chart above, which task has the potential to cause the GREATEST IMPACT on the project’s OVERALL DURATION?

1 point

Sales

Sales and Fundraising

Fundraising

Creative and Finance