Figure 4: Cumulative Probability Curve for the duration of Project X According to the cumulative probability curve above, what is the probability that this project will take AT LEAST 25 weeks to complete?

Question 7
Figure 4: Cumulative Probability Curve for the duration of Project X

According to the cumulative probability curve above, what is the probability that this project will take AT LEAST 25 weeks to complete?

1 point

10%

35%

50%

90%