Figure 4: Cumulative Probability Curve for the duration of Project X According to the cumulative probability curve above, what is the probability that this project will take AT LEAST 25 weeks to complete?
Question 7
Figure 4: Cumulative Probability Curve for the duration of Project X
According to the cumulative probability curve above, what is the probability that this project will take AT LEAST 25 weeks to complete?
1 point
10%
35%
50%
90%