Consider the project detailed in the table above
Question 5
Figure 2: Table for Project X
Consider the project detailed in the table above. Assume every task begins as soon as possible, but lasts its MINIMUM duration. What is the duration of this project as a whole?
1 point
6 weeks
10 weeks
19 weeks
30 weeks