Figure 4: Cumulative Probability Curve for the duration of Project X According to the cumulative probability curve above, what is the probability that this project will be completed within 55 weeks?
Question 8
Figure 4: Cumulative Probability Curve for the duration of Project X
According to the cumulative probability curve above, what is the probability that this project will be completed within 55 weeks?
1 point
10%
35%
50%
90%