Question 9 If a task in a given project has a criticality index of 95%, what does this number say about that task?
Question 9
If a task in a given project has a criticality index of 95%, what does this number say about that task?
1 point
This task occurs before 5% of the other tasks on the critical path
The duration of that task is likely to be 95% of the overall duration of the project
This task is highly likely to be on the critical path of a project and should be monitored closely
This task is more critical than 95% of the other tasks in the project