Select all of the characteristics of a punch list
1. Question 1 Select all of the characteristics of a punch list 1 / 1 point An activity to ensure all clients requirements are met List of contractors used on a…
1. Question 1 Select all of the characteristics of a punch list 1 / 1 point An activity to ensure all clients requirements are met List of contractors used on a…
5. Question 5 Once all punch list items are complete and have been approved by the client, the final Punch-List review will be handed over to the project manager for…
4. Question 4 The role of the project manager is to compile all of the individual punch lists items in an organized manner that can be ticked or punched off…
6. Question 6 Which of these work packages have overrunning budget? (Select all that apply) 1 / 1 point A.10 Work packages are considered overrunning budget if the CPI of…
5. Question 5 Which of these work packages are within budget? 1 / 1 point A.10 A.20 B.10 B.20 CPI = BCWP (B.10) / ACWP (B.10) =…
4. Question 4 What is the CPI for the work package B.20 ? 1 / 1 point 0.856 0.937 0.909 1.233 CPI = BCWP (B.20) / ACWP…
3. Question 3 What is the CPI for the work package A.20 ? 1 / 1 point 0.856 0.937 0.909 1.233 CPI = BCWP (A.20) / ACWP…
4. Question 4 Choose the 4 parameters needed to understand EVM 1 / 1 point BCWP BCAC BDWD BCWS ACWP
5. Question 5 Cost Variance = BCWP – ACWP 1 / 1 point True False
2. Question 2 EVM = % complete x budget of the account 1 / 1 point True False