Online Course Support

Consider the project detailed in the table above

Question 5
Figure 2: Table for Project X

Consider the project detailed in the table above. Assume every task begins as soon as possible, but lasts its MINIMUM duration. What is the duration of this project as a whole?

1 point

6 weeks

10 weeks

19 weeks

30 weeks