Figure 2: Network Diagram for Project X Which tasks will be critical if the Sales task takes 7 weeks instead of 6?
Question 6
Figure 2: Network Diagram for Project X
Which tasks will be critical if the Sales task takes 7 weeks instead of 6?
1 point
Creative, Sales, and Finance
Creative, Sales, and Finance/HR
Creative, Fundraising, and HR
Strategy, Marketing, and Finance