Figure 2: Network Diagram for Project X If the IT task takes 6 weeks instead of 5, what will be the earliest possible completion time for this project?
Question 7
Figure 2: Network Diagram for Project X
If the IT task takes 6 weeks instead of 5, what will be the earliest possible completion time for this project?
1 point
14 weeks
15 weeks
16 weeks
17 weeks