Online Course Support

Figure 2: Network Diagram for Project X If the IT task takes 6 weeks instead of 5, what will be the earliest possible completion time for this project?

Question 7
Figure 2: Network Diagram for Project X

If the IT task takes 6 weeks instead of 5, what will be the earliest possible completion time for this project?

1 point

14 weeks

15 weeks

16 weeks

17 weeks