Question 3 The probability of risk B is 0.5, with an impact score of 80. What is Risk B’s Risk Score?
Question 3The probability of risk B is 0.5, with an impact score of 80. What is Risk B’s Risk Score? 1 point 0.4 4 40 400
Question 3The probability of risk B is 0.5, with an impact score of 80. What is Risk B’s Risk Score? 1 point 0.4 4 40 400
Question 2Which of the following industries faces the MOST risk when it comes to demand and technology uncertainty? 1 point Precious metals Software Construction Mining
Question 1
Referring to Loch, DeMeyer, and Pich’s (2006) description of sources of uncertainty, which of the following scenarios most likely provides UNFORESEEABLE uncertainties?
1 point
Tesla motors planning to develop a new battery technology in 2016
Zara apparel developing 2016’s clothing collection
Apple releasing the next iPhone
The Olympic games in Rio
Question 10The backward pass is used to determine the Latest Start Time (LST) and Latest Finish Time (LFT) of tasks. The LFT of a task is the _____ of the…
Question 9Which of the following describes an “as soon as possible” schedule? 1 point Benefits on costs, but downside on time Constrained by time so compromise costs early on to…
Question 8What is the main goal of crashing a project activity? 1 point To create less risk associated with the project To create less slack in the project To increase…
Question 7Figure 2: Network Diagram for Project X If the IT task takes 6 weeks instead of 5, what will be the earliest possible completion time for this project? 1…
Question 6Figure 2: Network Diagram for Project X Which tasks will be critical if the Sales task takes 7 weeks instead of 6? 1 point Creative, Sales, and Finance Creative,…
Question 5Figure 2: Network Diagram for Project X What are the tasks along this project’s critical path? 1 point Creative, Sales, and Finance Creative, Fundraising, and HR Strategy, Sales, and…
Question 4Figure 1: Design/Dependency Structure Matrix for Project X According to the pictured Design/Dependency Structure Matrix, Task 4 is dependent on which tasks? 1 point Task 2 only Tasks 2…